Thames Tunnel Project
This webpage contains information regarding the Thames
Tunnel project, the different consultation events, the Council’s
responses and the Infrastructure Planning Commission (IPC) Process.
Please note that this webpage will be updated as the project
progresses.
The proposed Thames Tunnel will capture the flows of storm
sewage from 34 sewer overflow points along the River Thames. The
tunnel will run approximately 32 kilometres (20 miles) through the
heart of London, and up to 75 meters beneath the River Thames,
broadly following the path of the river. In Autumn 2008, Thames
Water began the process of consulting all the affected boroughs,
and other pan-London stakeholders such as the Environment Agency
and Greater London Authority. Inputs from this consultation were
taken into account in the site assessment methodology. Communities
were consulted in January 2011 (Phase One consultation) and are
currently consulted on Phase Two consultation before further
decisions are taken. The target date for the submission of planning
application is the end of June 2012, the enabling works will
commence in 2013 with completion of the project by 2020.
The Council has produced a Statement on the Thames
Tunnel.
Thames Tunnel Update: Phase 2 Consultation
Phase 2 consultation on the Thames Tunnel started on Friday 4
November. The consultation documents can be found on the
Thames Tunnel website. Consultation runs until 10 February.
A hard copy of the documents can be also seen in the
planning information office of the Town Hall. A series of
exhibitions have taken place close to the proposed sites. The
Council has produced a draft response which can be seen below,
under the section "Responses to previous consultations on the
Thames Tunnel Project".
|
Thames Tunnel: Statement on Cremorne
Gardens
Thames Tunnel and the Royal Borough agree that, subject to
further consideration and approval, the Thames Tunnel Works can be
facilitated without using Cremorne Gardens. The Royal Borough and
Thames Tunnel are currently having productive discussions regarding
the detailed design of the scheme which would locate any Thames
Tunnel works within the existing waste transfer station. These
proposals will be presented at the Phase 2 consultation.
Shortlisted sites in the Royal Borough
Please note that Cremorne Wharf is a safeguarded wharf and is
also the Royal Borough’s only licensed waste management site. These
uses cannot be lost permanently without ‘like for like’
replacement. This may lead to difficulties with the use of the
Wharf for construction and access purposes. The Council will not
agree to the use of Cremorne Gardens as a temporary access route to
the proposed works on the Cremorne foreshore. The Gardens are an
invaluable local asset and the Council will resist any attempt to
use them in connection with the Thames Tunnel. On this basis
another access route must be found. Discussions are taking place
between Thames Water and the Royal Borough to identify a viable
alternative access.
The Council has serious reservations about the likely negative
impact of the proposed lane closure on the Embankment upon the
Borough’s road network and the likely impact of the works to the
Embankment foreshore upon the ecological and amenity value of
Ranelagh Gardens and the Chelsea Embankment. Moreover, Royal
Hospital is a Grade I Listed Building, the gardens to the Royal
Hospital and Ranelagh Gardens are both listed, the embankment wall
is Grade II listed and these works will impact on their setting,
the character and appearance of the conservation areas and on views
to and from the river – the Tunnel structures and associated works
therefore need to be considered very carefully.
For frequently asked questions about the Thames Tunnel
Consultation, please see the
Thames Water website. The Council has submitted a
formal response to the Thames Tunnel Consultation - Phase
One which could be downloaded below but we would like to
encourage our residents to respond to the consultation too.
Meetings
The Council are holding meetings with Thames Water to
discuss the development of the Thames Tunnel Project. The minutes
of the meetings can be downloaded below.
Responses to previous consultations on the Thames Tunnel
Project
The IPC process
The Secretary of State announced in September 2010 that
development consent for the project should be dealt with under the
regime for nationally significant infrastructure projects
established by the Planning Act 2008.
The IPC process involves the following stages:
- Pre-application: Thames Water will develop
their proposals and will consult widely. The Council will be
consulted on the statement of community consultation and
participate in pre-application discussions. The Council will also
begin the evaluation of the local impacts and start working in the
Local Impact Report (LIR) to identify the social, environmental and
economic impacts of the project and any potential mitigation and
compensatory measures.
- Acceptance by the IPC: the IPC has 28 days to
decide whether there has been an effective consultation and whether
the application meets the required standards. The Council can make
representations to the IPC regarding the adequacy of the
consultation carried out. If the application is accepted, the IPC
will invite the Council to submit the LIR.
- Pre-examination (two to three months):
Commissioner(s) will be appointed to assess the issues and will
hold preliminary meetings and set a timetable. The preliminary
meetings will be procedural decisions on how the application is to
be examined. The Commission will set out the deadline for the
submission of the LIR.
- Examination: the IPC has six months to carry
out the examination. The Council will submit the LIR and make
representations.
- Decision: a decision on the proposal is issued
within three months, with a statement of reasons.
- Post-decision: There is a six-week period for
legal challenge.
Exceptional Hardship Policy
Thames Water have established an Exceptional Hardship
Procedure (EHP) for those who can prove they urgently need to sell
their property, but are unable to do because of the Thames Tunnel,
as currently proposed, and that they are suffering exceptional
hardship as a result. The information is available on Thames
Water's website and consists of an application form, a
guide to the application form and frequently asked questions. Hard
copies are available at the local libraries. If you would like more
copies of the information or have any questions, please contact
Victoria Phillips at victoria.phillips@tidewaytunnels.co.uk
or 0203 147 7783.
Please note that this applies to all riparian
boroughs along the Thames and its inclusion on our website does not
necessarily indicate that such properties exist in the Royal
Borough
If you have any questions regarding the content of this webpage
please e-mail the Planning Policy Team at planningpolicy@rbkc.gov.uk.
Page last updated 18 April 2012