Questions & answers
Why was so much work going on in Exhibition Road?
We had originally designed our workflow to
make the minimum disruption to residents and businesses in
Exhibition Road by a staged approach. But we had to modify our
original plans to make space for National Grid, EDF, Thames Water,
the V&A’s frontage refurbishment and a number of building works
to properties around South Kensington that were carried out
during our works.
Why did it take so long?
The work was slow because it was meticulous,
with every single granite block checked and laid by hand to tiny
tolerances. Balfour Beatty and their sub contractors laid a unique
road surface that will last for generations to come. It’s a bit
like making a giant complicated three dimensional jigsaw. But they
delivered the work to schedule.
Why did the parking arrangements change so often?
We asked Balfour Beatty to provide
resident parking spaces in the road wherever and whenever possible.
We tried to give advance notice when we needed to suspend spaces,
but it was not always possible to do this when other contractors
were involved. During the project resident permit holders of
both Westminster and the Royal Borough were able to park in
available bays anywhere in the entire length of Exhibition
Road.
How was the surface laid?
Once the old road surface had been stripped
and prepared, the utilities ducts, cables and pipes were checked
before the concrete base was laid. Then we had to wait for the
concrete to cure, and to make double sure that the base had
not impacted on the cabling, before we set out the
individual blocks.
How much did it cost and who is paying?
The total cost of the project was £29.2 million, of which the
first completed phase around South Kensington station cost £6.55
milllion.
The Royal Borough of Kensington and Chelsea is paying £14.6
million, The Mayor of London £13.4 million and Westminster City
Council £1 million. The remaining £200,000 is coming from various
other sources including English Heritage.
Were any trees removed as part of the project?
No, we increased the number of trees overall by keeping as
many existing trees as possible and planting new ones wherever
possible. There are some restrictions to where we can plant
trees. We have to avoid the tunnel running up the Western side
of Exhibition Road and the utilities already in place underground.
See tree plan here
How will the new traffic management affect pedestrian
safety?
The streetscape changes mean that traffic is restricted to
the east side of Exhibition Road, away from the busiest pedestrian
flow between South Kensington Station and the Science Museum. We
have improved the pedestrian crossings by making them
wider, to accommodate larger numbers of pedestrians.
Will those with a disability be able to safely use the
area?
Yes, this is a key priority for us. Kerbs can be difficult for
many and a single surface will significantly improve access for
those using wheelchairs, push chairs and motorised buggies. The
wide safe pedestrian area will allow vulnerable members of the
community to move around in confidence away from moving traffic.
Black cast iron drainage covers along each side of the vehicle area
will visually separate pedestrian areas from moving traffic, which
is particularly useful for young children and the partially
sighted.
Won’t blind and partially sighted people
potentially be put at risk by the single surface?
We will install wide strips of corduroy tactile – ridged
paving often used to demark steps – alongside the drainage
gulley to alert blind people to the edge of the ‘safe’ area. At the
start of the design process, the Royal Borough appointed
an access consultant and, throughout the design process, we
have consulted with groups through a dedicated ‘Access Group’,
to ensure Exhibition Road is accessible to all users.
We employed specialist consultants to carry out in-situ
testing of the delineator; the results can be seen in the
report
Exhibition Road Corduroy Delineator Testing [PDF]
(warning: large file size 1.94Mb)
Will traffic speed be reduced along Exhibition Road?
We have introduced a 20 mph speed limit on the road, and we
expect the scheme to reduce traffic by approximately 30 per
cent to the south of Prince Consort Road. The removal of
street clutter, such as conventional traffic signals, barriers,
signs and road markings, will encourage motorists to slow down when
they enter the road and engage with their surroundings.
Will you be adding signage to tell visitors and tourists where
to go?
We are working with TfL on improving signage and
way-finding in the area in line with their ‘Legible
London’ principles.