On 4th September 2024, the Grenfell
Tower Inquiry published the findings of Phase 2 of its inquiry. The
Council accepted the findings in full. The report was commissioned
to ascertain the implications for the Council. The Phase 2 Report
discussed risk management and the assurance processes
management.
The Chair invited Maxine Holdsworth, Chief
Executive of the Council, to present the report to Committee
who;
- Disclosed that the Phase
2 Report made recommendations in relation to the Tenant Management
Organisation (TMO). Following consultation with tenants in 2018,
the Council took over responsibility for housing management
following and the relevant recommendations in relation to the TMO
would be addressed by Housing Management section.
- Highlighted the
report’s criticism of the Council’s Building Control
Department and the Council’s actions in the aftermath of the
fire.
- Explained the timetable
for the Council to provide a final response which would completed
following consultations with survivors, the bereaved and the local
community.
- announced that the
Council would be undertaking a review of the following;
- The Risk management
strategy; and
- The Strategic risk
register; and
- The Internal Audit Plan
and
- The Annual Governance
Statement
- Emphasised that the
Council had introduced a rota in relation to emergency responses
with every role populated, designated staff trained in their role,
and the rota is live 24 hours a day 365 days a year. The Chief
Executive added that she could be contacted at any time where
necessary and that the Council’s preparedness had improved
considerably since 2017 but there was still work to be
undertaken.
- The Council was required
to report to the London Resilience Board which is overseen by the
Mayor of London.
- Disclosed that there was
no cladding on Council owned housing blocks that required to be
removed. Within the borough, there were privately owned blocks that
were undergoing work to remove unsuitable cladding.
- That the Council has
received assistance from the Centre for Scrutiny and the British
Standards Institute in developing mechanisms to improve both
scrutiny and safety mechanisms.
The Committee discussed its own role in terms
of oversight noting that;
- Risk management was a
constant theme considered by the Committee but that it was always a
work in progress. The Committee concluded that it needed to
undertake work on the risk register. David Hughes, the
Director of Audit, Fraud Risk and Insurance acknowledged that the
risk management strategy had been a work in progress adding that
the report would help the Council formulate a strategy.
- That the Committee met
five times a year and discussed topics scheduled for particular
meetings months in advance. The Committee suggested that officers
should bring topics to the Committee where there were serious
issues rather than wait until the relevant item was scheduled.
Committee members also questioned the value of items that where
‘to note.’ The Director of Audit, Fraud, Risk and
Insurance accepted this and suggested that the Committee’s
work programme be reviewed, and members provide feedback on topics
they would like to consider.
Action by; Senior Governance
Co-Ordinator and Director of Audit, Fraud, Risk and
Insurance.
- The length of reports
should be reduced, where possible, and be more concise. The
Committee also suggested that certain information could be
circulated offline and did not require consideration at the
Committee.
- Specialists should be
invited to Committee meetings to assist the Committee in its
understanding on particular topics, it was also important to invite
representatives of external stakeholders to meetings.
- Contrasted how risk
management was treated in the private sector compared to the
Council drawing attention to the information on fire doors. The
Committee were given differing answers on the number of fire doors
and how many had been replaced. The Committee emphasised that
Internal Audit must be robust including in terms of oversight of
third parties providing services of the Council.
- The Chief Executive
responded that, in relation fire doors, this was an ongoing
project, and a definitive response would be provided to the Housing
and Communities Select Committee and would be part of the
Council’s final response.
- The
Chief Executive then explained that there was a Risk Management
Board which she chaired, and the Head of Internal Audit reported to
it. Where Internal Audit has issued a rating of ‘limited
assurance’ or ‘no assurance.’ The Board would
review the issues that resulted in the rating being issued. The
manager of the Department would be required to account. The Chief
Executive added that as part of improved accountability, the
relevant manager should also report to the Committee, including
attending meetings, as well as the Lead Director.
- That the problems with
the TMO identified in the Phase 2 Report were not reported to the
Committee. The Director of Audit, Fraud, Risk and Insurance,
acknowledged the problems and stressed that there had been
improvement in reporting of risks.
The
Strategic Risk Register now contains;
·
risks relating to statutory compliance with health and safety
requirements in the Council’s tenanted properties; and
·
Emergency planning and resilience risk; and
·
safety and wellbeing of residents affected by the Grenfell
Tragedy
- The Procurement Act 2023
which comes into force in February 2025 will assist in providing a
framework for contract management including greater transparency on
contracts that are not performing or where they are problems.
- The Council was
criticised for not sufficiently catering for those from diverse
backgrounds and the Grenfell Inquiry heard from residents who
alleged social and racial discrimination. The Chief Executive
explained that this criticism stemmed from the manner that the
Council initially reported on households affected by the fire. This
had been addressed in the emergency response plan whereby
information on specific household’s needs would be collated
such as religious observance and specific needs. The Resilience
Team worked with local organisations and communities to ensure that
the emergency systems and processes are tailored to residents.
- The predecessor Chief
Executive commissioned the Equalities and Human Rights Commission
(EHRC) to review the Council’s equalities, diversity and
inclusion policies. The subsequent report informed the
Council’s Equality Strategy which was now in the process of
being refreshed. The Council had also adopted Fairness Action Plan
which was presently subject to consultation. action plan.
- The Chair thanked the
Chief Executive for her presentation, concluded the discussion and
noted the report.