Case reference: PP/15/01473
Address: Gordon House, The Orangery and Creek Lodge, Royal Hospital, Royal Hospital Road, LONDON, SW3 4SR
Ward: Royal Hospital
Polling district: 16
Listed Building Grade: 2
Conservation area: Royal Hospital

Applicant details

Applicant's name: Candy
Applicant company name: DP9 Ltd
Contact address: 100 Pall Mall London SW1Y5NQ

Proposal details

Application type: PP (Planning permission)
Proposed development Construction of basement plant area associated with swimming pool. External steps to move from east side facade at Gordon House and landscaping
Date received: 11 Mar 2015
Registration date:
(Statutory start date)
17 Mar 2015
Public consultation ends: 17 Apr 2015
Application status: Decided
Target date for decision: 12 May 2015

Decision details

This case has not yet been decided.

Decision: Grant Planning Permission/Consent
Decision date: 15 May 2015
Conditions and reasons:

1)

Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.

2)

Compliance with approved drawings Except as required by condition 10, the development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.

3)

Construction Traffic Management Plan (CTMP) No development shall commence until a Construction Traffic Management Plan has been submitted to and approved in writing by the local planning authority. The statement should include: a) routeing of demolition, excavation and construction vehicles, including a response to existing or known projected major building works at other sites in the vicinity and local works in the highway; b) access arrangements to the site; c) the estimated number and type of vehicles per day/week; d) details of any vehicle holding area; e) details of the vehicle call up procedure; f) estimates for the number and type of parking suspensions that will be required; g) details of any diversion or other disruption to the public highway during preparation, demolition, excavation and construction work associated with the development; h) work programme and/or timescale for each phase of preparation, demolition, excavation and construction work associated with the development; i) details of measures to protect pedestrians and other highway users from construction activities on the highway; j) a strategy for coordinating the connection of services on site with any programme work to utilities upon adjacent land; and k) where works cannot be contained wholly within the site a plan should be submitted showing the site layout on the highway including extent of hoarding, position of nearby trees in the highway or adjacent gardens, pedestrian routes, parking bay suspensions and remaining road width for vehicle movements. The development shall be carried out in accordance with the approved Construction Traffic Management Plan.
Reason - To minimise the impact of construction works upon highway safety and nearby residents' enjoyment of their properties in accordance with the Subterranean Development SPD and policies CT1 and CL5 of the Core Strategy. It is necessary for the condition to be on the basis that 'No development shall commence until' as c

4)

Professional management of engineering works The construction works shall be supervised throughout their duration by Michael Coombs (BSc MSc DIC FIStructE MCONSE) of Alan Baxter & Associates LLP. In the event that the appointed engineer ceases to perform that role for whatever reason before the construction works are completed those works will cease until a replacement Chartered Civil Engineer (MICE) or Chartered Structural Engineer (MI Struct.E) has been appointed to supervise their completion and their appointment confirmed in writing to the Local Planning Authority. At no time shall any construction work take place unless an engineer is at that time currently appointed and their appointment has been notified to this Authority in accordance with this condition.
Reason - The details are considered to be material to the acceptability of the proposal, and for safeguarding the amenity of neighbouring residential properties and to comply with the Subterranean Development SPD and policy CL7 of the Core Strategy.

5)

Considerate Constructors Scheme (CCS) No development shall commence until such time as the lead contractor, or the site, is signed to the Considerate Constructors Scheme (CCS) and its published Code of Considerate Practice, and the details of (i) the membership, (ii) contact details, (iii) working hours as stipulated under the Control of Pollution Act 1974, and (iv) Certificate of Compliance, are clearly displayed on the site so that they can be easily read by passing members of the public, and shall thereafter be maintained on display throughout the duration of the works forming the subject of this permission.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Subterranean Development SPD and policy CL5 of the Core Strategy. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.

6)

Noise from building services plant and vents Noise emitted by all building services plant and vents shall not exceed a level 10dBA below the existing lowest LA90(10min) background noise level at any time when the plant is operating, and where the source is tonal it shall not exceed a level 15dBA below. The noise emitted shall be measured or predicted at 1.0m from the facade of the nearest residential premises or at 1.2m above any adjacent residential garden, terrace, balcony or patio. The plant shall be serviced regularly in accordance with the manufacturer's instructions and as necessary to ensure that the requirements of the condition are maintained. If at any time the plant is determined by the local planning authority to be failing to comply with this condition, it shall be switched off upon written instruction from the local planning authority and not used again until it is able to comply.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Core Strategy.

7)

Anti-vibration mounts for air-conditioning/ extraction equipment The plant shall not operate unless it is supported on adequate proprietary anti-vibration mounts to prevent the structural transmission of vibration and regenerated noise within adjacent or adjoining premises, and these shall be so maintained thereafter.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Core Strategy.

8)

Odours from swimming pool ventilation/ filtration equipment Fumes or odours expelled from any flue serving the hygiene plant or providing ventilation to the swimming pool area shall not be detectable at the property boundary. If at any time the extraction plant is determined by the local planning authority to be failing to comply with this condition, it (or the source equipment) shall be switched off and not used again until it is able to comply.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Core Strategy.

9)

Flood Risk The development shall incorporate the mitigation measures as set out detail in the Flood Risk Assessment prepared by Water Environment Limited, dated 18th February 2015:
Reason - To protect future occupants from the risk of basement flooding.

10)

Submission of details (Full PP) Detailed drawings or samples of materials as appropriate, in respect of the following, shall be submitted to and approved in writing by the local planning authority before the relevant part of the work is begun, and the works shall not be carried out other than in accordance with the details so approved and shall thereafter be so maintained: (a) Materials to be used for the outbuilding to the south west corner of the site; and (b) Detailed plans, including elevations, at a scale of no less that 1:20 of the outbuilding to the south west corner of the site.
Reason - To accord with the development plan by ensuring that the character and appearance of the area are preserved and living conditions of those living near the development suitably protected.

11)

Black painted railings The railings to the car ramp and new stairs to the east of Gordon House shall be painted black, and so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL6 of the Core Strategy.

12)

Landscaping The development shall be shall be carried out in accordance with the details contained within the Landscape Design Statement prepared by applied landscape design, Report ALD633_RP910 Rev. P09 dated May 2015.
Reason - To protect the appearance and amenity of the area and to accord with policies of the development plan, in particular policy CR6 of the Core Strategy. ÿ

Informatives:

1)

Enforcement of Conditions (PP)
Your attention is drawn to the Conditions of this Permission and to the Council's powers of enforcement, including the power to serve a Breach of Condition Notice under the Town and Country Planning Act 1990, as amended. All Conditions must be complied with. If you wish to seek to amend a Condition you should apply to do so under s.73 of the Act, explaining why you consider it is no longer necessary, or possible, to comply with a particular condition.

2)

Variations to Approved Drawings
Planning permission is hereby granted for the development as shown on the approved drawings. Any variation to the approved scheme may require further permission, and unauthorised variations may lay you open to planning enforcement action. You are advised to seek advice from the Directorate of Planning and Borough Development, before work commences, if you are thinking of introducing any variations to the approved development. Advice should urgently be sought if a problem occurs during approved works, but it is clearly preferable to seek advice at as early a stage as possible. Use the following link to see how advice can be obtained: Planning Advice Service

3)

GTD/Pre-app/At submission Est.G/No amend
To assist applicants in finding solutions to problems arising in relation to their development proposals the Local Planning Authority has produced planning policies, and provided written guidance, all of which are available on the Council's website. A pre-application advice service is also offered. The scheme was submitted in accordance with advice provided through pre-application discussions.

4)

Floodline - Basements in Flood Zones1/2
You have been granted planning permission for a basement or extension to an existing basement. We strongly advise that you sign up to the free Flood Warning Direct service operated by the Environment Agency where you will receive a free warning by telephone, text or e-mail, by calling Floodline on 0845 988 1188 or going to Flood Warning Alerts

Committee details

Decision by: This case is currently due to be decided by the Planning Applications Committee.
Date:12 May 2015
Report item number:S25

Appeal details

This case has not been appealed.

Planning Inspectorate reference number:
Appeal received:
Appeal type:
Appeal procedure:
Appeal start date:
Deadline for comments to be received by the Planning Inspectorate:
Appeal decision:
Appeal decision date:

Contact details

Planning case officer: Alison Long
Planning team: South
Email: [email protected]
Telephone: 020 7361 3012

Comment on this application