1)
Time limit
The works hereby granted shall be begun before the expiration of three years from the date of this consent.
Reason - As required by Section 18 of the Planning (Listed Buildings and Conservation Areas Act) 1990, to avoid the accumulation of consents.
2)
Compliance with drawings
The works forming the subject of this consent shall not be carried out except in complete accordance with the details shown on submitted plans and shall be so maintained.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building .
3)
Submission of details
Detailed drawings or samples of materials as appropriate, in respect of the following, shall be submitted to and approved in writing by the local planning authority before the relevant part of the work is begun, and the works shall not be carried out other than in accordance with the details so approved and shall thereafter be so maintained:
a) Brick sample panels comprising bricks salvaged from the closet wing and new bricks matched to existing to be viewed in situ. Pointing in mortar mix based on analysis to be included.
b) Mortar analysis of historic mortar and pointing, to form basis for new mortar joints.
c) Evidence of reclamation and storage of bricks from demolished element of closet wing.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
4)
Work to match retained fabric
All new works and works of making good to the retained fabric, whether internal or external, shall be finished to match the adjacent work with regard to the methods used and to colour, material, texture, and profile.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
5)
Works to match - Sample panels required
Sample panels of facing brickwork showing the proposed colour, texture, facebond and pointing shall be provided on site, and approved in writing by the local planning authority before the relevant parts of the approved works are commenced, and the sample panels shall be retained on site until the work is completed in accordance with the panel(s) so approved.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
6)
Brick bond
The brickwork bond shall match the original bond on the building.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
7)
Pointing, re-pointing, and jointing
The mortar mix shall match the original construction mortar of the building with regard to the grading of the aggregate, finish, and colour. The mortar must be lime based (NHL as per EN459) with no cement content. The pointing profile shall match the original profile on the building.
If the original pointing no longer exists, details of the re-pointing profile should be submitted to and approved in writing by the local planning authority before any such re-pointing takes place.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
8)
Retention of fabric
All existing fabric including existing wall and ceiling plasterwork shall be retained, unless notated otherwise on the drawings approved under this consent.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
9)
Demolition and stability
Before any work is undertaken in pursuance of this consent to demolish any part of the building, such steps shall be taken and such works carried out as shall, during the progress of works permitted by this consent, secure the safety and stability of all parts of the building to be retained.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
10)
Partitions
All partitions hereby granted consent shall be of lightweight construction, easily removable, and be so maintained.
Reason:- To preserve the special architectural character and heritage significance of the listed building and comply with Policy CL4 of the Local Plan 2019.
11)
Salvage and Reuse of Bricks From Closet Wing
The demolition of the outward fa╪ade of the closet wing is dependent upon the historic bricks being salvaged and reused in the new brickwork elements, and so
be maintained.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.
12)
Salvage and Reuse of Historic Window from Lower Ground Floor Closet Wing
The lower ground floor window to be carefully removed prior to demolition, stored,and reintegrated into the closet wing, and so be maintained.
Reason - In order to safeguard the special architectural or historic interest and heritage significance of the building and comply with policy CL4 of the Local Plan 2019.