Decision - Employers Agent Services for the Maxilla Project: Contract Award ED06431
Decision details
Employers Agent Services for the Maxilla Project: Contract Award ED06431
Decision Maker: Executive Director of Housing & Social Investment
Decision status: Implemented
Is Key decision?: No
Is subject to call in?: No
Purpose:
Decision to appoint Employers Agent for construction of the Maxilla Health & Wellbeing Hub and Community Space.
Decision:
The Executive Director of Housing and Social Investment AGREED to approve the direct award, without competition of a contract to Philip Pank Partnership LLP at a value of £222,000 (Inc. VAT) for the provision of Employers Agent services, for the development of the Maxilla Adult Social Care and Community Hub Bays, 17-19 Maxilla Walk.
Publication date: 14/05/2025
Date of decision: 14/03/2023
Accompanying Documents: