!DOCTYPE html> The Royal Borough of Kensington and Chelsea | Planning Search

Planning Search

Back to search results

Property details

Case reference: PP/24/01335
Address: 56 Lansdowne Road, LONDON, W11 2LR
Ward: Norland
Polling district: 11
Listed Building Grade: N/A
Conservation area: Ladbroke

Applicant details

Applicant's name: Lamotte
Applicant company name: ADL Planning Pty Ltd
Contact address: 1 The Arbory Plumpton Lane Great Plumpton PR4 3NH

Proposal details

Application type: PP (Planning permission)
Proposed development Infill below cantilevered rear terrace at lower ground floor rear elevation, erection of single storey rear extension at lower ground floor level with associated alterations to lower floor level of dwelling and existing sunken garden, provision of spiral staircase, replacement of rear window at upper ground floor level with timber sash, provision of ASHP within front garden at lower ground floor level replacing lower-level terraced garden, and provision of rooflights to rear and side roofslopes at main roof level
Date received: 01 Mar 2024
Registration date:
(Statutory start date)
01 Mar 2024
Public consultation ends: 29 Mar 2024
Application status: Decided
Target date for decision: 26 Apr 2024

Decision details

This case has not yet been decided.

Decision: Grant Planning Permission/Consent
Decision date: 17 Apr 2024
Conditions and reasons:

1)

Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.

2)

Compliance with approved drawings The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.

3)

Code of Construction Practice No development shall commence until: An Appendix A Checklist and Site Construction Management Plan (SCMP) for the development have both been submitted to, and approved in writing, by the Council's Construction Management Team, and then B) Copies of the approved Checklist and Plan, and their written approval, have been submitted to the local planning authority to be placed on the property record. The development shall be carried out in accordance with the Appendix A Checklist and SCMP so approved, or in accordance with a subsequent Checklist or SCMP as may be approved under this condition. Note - The Council's Construction Management Team work independently of the planning department. For further information regarding the Code and how the required details should be submitted to them, the Council's Construction Management Team can be contactedÿon email at:ÿ[email protected] or tel: 020 7361 3002
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.

4)

Sustainable Urban Drainage System (SuDS) (for major and minor applications - implementation) During construction of the development hereby permitted the submitted Sustainable Urban Drainage System (SuDS) shall be fully implemented and maintained thereafter.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.

5)

Arboricultural Impact Assessment - Compliance The development shall be carried out in accordance with the approved Arboricultural Impact Assessment, prepared by Hayden's Arboricultural Consultants dated 25 January 2024, and shall be so maintained.
Reason - To ensure the proposals have an acceptable impact on trees in the Borough, in accordance with policy CR6 of the Local Plan 2019.

6)

Noise from building services plant and vents Noise emitted by the air conditioning condensing unit hereby permitted shall not increase the lowest existing measured background LA90(15min) level measured or predicted at 1.0m from the nearest residential window and/or at a height of 1.2m above any adjacent residential garden, terrace, balcony, or patio at any time when the plant is operating. The plant shall be mitigated as per the details contained within the CSG Acoustic Report, Ref CSGA-2161-T1, Dated 28 February 2024, submitted in support of this planning application. Furthermore, the plant will operate in Silent 1 Mode between the hours of 23:00 and 07:00 daily. The plant and associated mitigation shall be serviced regularly in accordance with manufacturer's instructions and as necessary to ensure that the requirements of the condition are maintained. If at any time the plant is unable to comply with this Condition, they shall be switched off and not used again until it is able to comply.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Local Plan 2019.

7)

Anti-vibration mounts for air-conditioning/ extraction equipment The plant shall not operate unless it is supported on adequate proprietary anti-vibration mounts to prevent the structural transmission of vibration and regenerated noise within adjacent or adjoining premises, and these shall be so maintained thereafter.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Local Plan 2019.

8)

Conservation rooflights The rooflight(s) shall be of a traditional conservation type, flush with the roof and slim framed, and so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL2 of the Local Plan 2019.

9)

Windows in painted timber The windows hereby permitted shall be framed in painted timber, and be so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL2 of the Local Plan 2019.

Informatives:

1)

Variations to Approved Drawings
Planning permission is hereby granted for the development as shown on the approved drawings. Any variation to the approved scheme may require further permission, and unauthorised variations may lay you open to planning enforcement action. You are advised to seek advice from the Directorate of Planning and Place, before work commences, if you are thinking of introducing any variations to the approved development. Advice should urgently be sought if a problem occurs during approved works, but it is clearly preferable to seek advice at as early a stage as possible. Use the following link to see how advice can be obtained: Planning Advice Service

2)

Care in the Conservation Area
This property is within a Conservation Area. All building works should, therefore, be completed with great care. External facing work and detailed treatment should be finished in a manner sympathetic to the existing building. If there is any doubt about the way in which work should be carried out, you should seek the advice of the Directorate of Planning and Place.

3)

Unique text
Due to the small-scale nature of the works, under best practice guidance MoL SPG 'The Control of Dust and Emissions from Construction & Demolition Sites' and the IAQM's 'Assessment of dust from demolition and construction' the site would be determined as 'Low Risk' with regards to dust impacts. Any Environmental Management Plans, Construction Management Plans or Construction Traffic Management Plans should reference these guidance documents and include a list of the appropriate mitigation measures to be utilised on site where necessary. The physical onsite inspection for the generation of dust and soiling effects will be sufficient in this case when utilised alongside other mitigation measures.

4)

GTD/Pre-app/At submission Est.G/No amend
To assist applicants in finding solutions to problems arising in relation to their development proposals the Local Planning Authority has produced planning policies, and provided written guidance, all of which are available on the Council's website. A pre-application advice service is also offered. The scheme was submitted in accordance with advice provided through pre-application discussions.

Committee details

Decision by: This case is currently due to be decided under delegated powers.

Appeal details

This case has not been appealed.

Planning Inspectorate reference number:
Appeal received:
Appeal type:
Appeal procedure:
Appeal start date:
Deadline for comments to be received by the Planning Inspectorate:
Appeal decision:
Appeal decision date:

Contact details

Planning case officer: Sarah Winter-Irving
Planning team: North
Email: [email protected]
Telephone: 020 7361 3012

Comment on this application

The consultation period for this application has ended.

Documents related to case PP/24/01335