1)
Time Limit
The development hereby permitted shall be begun before the expiration of three years from 11/11/2020, being the date of the original permission granted under ref. PP/20/00860.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.
2)
Compliance with approved drawings
The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.
3)
Submission of details (Full PP)
Notwithstanding Condition 2, prior to commencement of the relevant works, full particulars of the following shall be submitted to and approved in writing by the local planning authority and the development shall not be completed otherwise than in accordance with the details so approved:
(a) Detailed elevations clearly showing the design of the facades, distribution of the differing materials / brick pattern (approved under application reference CON/23/00683).
(b) Samples of all new bricks, stones and slate (approved under application reference CON/23/00683);
(c) Detailed drawings of all external door and window openings (including balustrades and manufacturers information);
(d) Details of the proposed roof constructions and details of the roofing materials;
(e) Boundary details of communal terraces and ground floor community use 'spill out' area;
(e) Drawings showing the location of proposed plant equipment and any enclosure;
(f) Drawings showing the location of any downpipes or ventilation flues.
Reason - To preserve the character and appearance of the area in accordance with policies of the development plan in particular policies CL1, CL2, and CL6 of the Local Plan 2019.
4)
Sample Panel
The development hereby approved shall be carried out in accordance with the sample panel submitted to, and approved by the Local Planning Authority under application reference CON/23/00683. The sample panel shall be retained on site until the construction work is completed and the development shall be carried out in accordance with the approved details.
Reason - To preserve the character and appearance of the area in accordance with policies of the development plan in particular policies CL1, CL2, and CL6 of the Local Plan 2019.
5)
Travel Plan - Details reserved
None of the community floorspace (Class D1) hereby approved shall be occupied until a travel plan has been submitted to, and approved in writing by, the local planning authority. The travel plan shall be monitored and reviewed in accordance with any targets within the plan, and such record made available upon request by the local planning authority.
Reason - To ensure the safe and sustainable movement of traffic on neighbouring highways, in accordance with policies of the development plan in particular policy CT1 of the Local Plan 2019.
6)
Delivery and Service Management Plan
Prior to the occupation of the development, a final Delivery and Service Management Plan (including hours of servicing) shall be submitted to, and approved in writing by the local planning authority and the development shall not be completed otherwise than in accordance with the details so approved, and so maintained thereafter.
Reason - To ensure that the development does not lead to the obstruction of adjacent streets, and to minimise the impact upon highway safety and nearby residents' enjoyment of their properties in accordance with policies CR7, CT1 and CL5 of the Local Plan 2019.
7)
Provide cycle storage prior to occupation
The development shall be carried out in accordance with the approved amended drawings under reference CON/22/01876, unless otherwise agreed in writing.
Reason - To ensure the safe and sustainable movement of traffic on neighbouring highways, in accordance with policies of the development plan in particular policy CT1 of the Local Plan 2019.
8)
Refuse and Recycling
Prior to occupation of the development, details of the refuse storage arrangements for the residential and community uses, including provision for the storage of recyclable materials, shall be submitted to and approved in writing by the local planning authority. The building shall not be occupied until the approved refuse storage arrangements are in place and all approved storage arrangements shall thereafter be retained.
Reason - In order to ensure that satisfactory provision is made for refuse storage and collection, in accordance with Policy 5.3 of the London Plan and Policy CE3 of the Local Plan 2019.
9)
Construction Traffic Management Plan (CTMP)
The development shall be carried out only in accordance with the approved Construction Traffic Management Plan, under reference CON/21/00510, unless otherwise agreed in writing by the Local Planning Authority. A one page summary of the requirements of the approved CTMP shall be affixed to the frontage of the site for the duration of the works at a location where it can be read by members of the public.
Reason - To minimise the impact of construction works upon highway safety and nearby residents' enjoyment of their properties in accordance with the Basements SPD and policies CL7, CT1 and CL5 of the Local Plan 2019.ÿ
10)
No music audible outside
No music, musical instruments, or loudspeakers shall be played or used within the community use floorspace forming the subject of this permission so as to be audible outside the premises outside the hours of 09.00 to 18.00 daily.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Local Plan 2019.
11)
Noise from building services plant and vents
Noise emitted by all building services plant and vents shall not exceed a level 10dBA below the existing lowest LA90(10min) background noise level at any time when the plant is operating, and where the source is tonal it shall not exceed a level 15dBA below. The noise emitted shall be measured or predicted at 1.0m from the facade of the nearest residential premises or at 1.2m above any adjacent residential garden, terrace, balcony or patio. The plant shall be serviced regularly in accordance with the manufacturer's instructions and as necessary to ensure that the requirements of the condition are maintained. If at any time the plant is determined by the local planning authority to be failing to comply with this condition, it shall be switched off upon written instruction from the local planning authority and not used again until it is able to comply.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Local Plan 2019.
12)
Anti-vibration mounts for air-conditioning/ extraction equipment
The plant shall not operate unless it is supported on adequate proprietary anti-vibration mounts to prevent the structural transmission of vibration and regenerated noise within adjacent or adjoining premises, and these shall be so maintained thereafter.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Local Plan 2019.
13)
Sound Insulation Between Dwellings
The sound insulation shall be installed and maintained only in accordance with the details so approved under reference CON/22/01876, unless otherwise agreed in writing. None of the dwellings shall be occupied until the approved insulation scheme has been fully implemented.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 and CE6 of the Local Plan 2019.
14)
Sound Insulation Between Community Use and Dwellings
Prior to fit out works of the community spaces, a scheme of sound insulation designed to prevent the transmission of excessive airborne and impact noise between the community floorspace and dwellings in the development, shall be submitted to, and approved in writing by the Local Planning Authority. The sound insulation shall be installed and maintained only in accordance with the details so approved. None of the dwellings shall be occupied until the approved insulation scheme has been fully implemented.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 and CE6 of the Local Plan 2019.
15)
Sound Insulation - Facade Construction
The facade construction, including glazing, with commensurate composite sound insulation performance predictions, shall be carried out in accordance with the details approved under reference CON/22/01876, unless otherwise agreed in writing by the Local Planning Authority.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 and CE6 of the Local Plan 2019.
16)
Amended Air Quality Impact Assessment Required
Prior to the occupation of the development, a revised Air Quality Assessment, containing a review of PM2.5 has been submitted to, and approved in writing by, the Local Planning Authority.
Reason - To comply with the requirements of the NPPF and policy CE5 of the Local Plan 2019 in ensuring that impact upon air quality in the area is minimised, in accordance with the London Councils 'Air Quality and Planning Guidance' recommended format. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
17)
Construction Environmental Management Plan (CEMP)
The development hereby approved shall be carried out in accordance with the Construction Environmental Management Plan submitted to, and approved in writing, by the Local Planning Authority under application reference CON/21/00510.
Reason - To comply with the requirements of the NPPF and policies CE3, CE5, CE6, and CL5 of the Local Plan 2019 in ensuring that effects upon air quality in the area are minimised and to accord with the Mayor of London's Best Practice Guidance 'Control of dust and emissions from construction and demolition'.
18)
Non-Road Mobile Machinery
Non-Road Mobile Machinery (NRMM) shall be used in accordance with the approved document under reference CON/21/00510, unless otherwise agreed in writing. All NRMM shall meet as minimum the Stage IIIA emission criteria of Direction 97/68/EC and its subsequent amendments unless it can be demonstrated that Stage IIIA equipment is not available. An inventory of all NRMM shall be registered on the NRMM register https://nrmm.london/user-nrmm/register. All NRMM shall be regularly serviced and service logs kept on site for inspection. Records shall be kept on site which details proof of emission limits for all equipment.
Reason - To comply with the requirements of the NPPF, policy 7.14 of the London Plan, and policy CE5 of the Local Plan 2019 in ensuring that impact upon air quality in the area is minimised, in accordance with the London Councils 'Air Quality and Planning Guidance' recommended format.
19)
Air Quality Monitoring
The development shall be carried out in accordance with the approved site-specific Dust & Air Quality Monitoring Plan under reference CON/21/00510, unless otherwise agreed in writing by the Local Planning Authority.
Reason - To comply with the requirements of the NPPF and policy CE5 of the Local Plan 2019 in ensuring that impact upon air quality in the area is minimised, in accordance with the London Councils 'Air Quality and Planning Guidance' recommended format.
20)
Considerate Constructors Scheme (CCS)
No development shall commence until such time as the lead contractor, or the site, is signed to the Considerate Constructors Scheme (CCS) and its published Code of Considerate Practice, and the details of (i) the membership, (ii) contact details, (iii) working hours as stipulated under the Control of Pollution Act 1974, and (iv) Certificate of Compliance, are clearly displayed on the site so that they can be easily read by passing members of the public, and shall thereafter be maintained on display throughout the duration of the works forming the subject of this permission.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements SPD and policy CL5 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
21)
Energy Performance
The development shall be constructed in accordance with the submitted Energy Statement 19-E065-011 Rev V1, demonstrating how the development will follow the hierarchy of energy efficiency, decentralised energy and renewable energy technologies to secure a minimum 35% reduction in CO2 emissions beyond the baseline of Part L of the Building Regulations 2013.
Prior to occupation of the development, evidence shall be submitted to the Local Planning Authority to demonstrate that the development has been carried out in accordance with the approved Energy Strategy unless otherwise agreed by the Local Planning Authority in writing.
Reason - To ensure that the development contributes to the attainment of sustainable development and to comply with policy CE1 of the Local Plan 2019.
22)
Sustainable Urban Drainage System (SuDS)
The development shall be carried out in accordance with the approved Sustainable Drainage Strategy, under reference CON/21/01164, unless otherwise agreed in writing by the Local Planning Authority.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.
23)
Contamination - Remediation method statement
The development shall be carried out in accordance with the approved Remediation Method Statement to address the results of the Site Investigation Scheme, under reference CON/21/01164, unless otherwise agreed in writing by the Local Planning Authority.
Reason - To ensure any risks from land contamination are minimised, and comply with the NPPF and development plan policies, in particular policy CE7 of the Local Plan 2019 and accord with CLR 11: Model Procedures for the Management of Land Contamination (Defra 2004) or the current UK requirements for sampling and testing.
24)
Contamination - Verification report
Prior to occupation, the measures in the approved Remediation Method Statement shall be implemented and a Verification Report (VR) shall be submitted to, and approved in writing by, the local planning authority. The VR shall include full details of requirements for ongoing monitoring and maintenance and be prepared in line with the Environment Agency's current Land Contamination Risk Management Guidance and Royal Borough of Kensington & Chelsea informatives/guidance or any subsequent updates. Ongoing monitoring and maintenance shall be implemented in line with the approved Verification Report]
Reason - To ensure any risks from land contamination are minimised, and comply with the NPPF and development plan policies, in particular policy CE7 of the Local Plan 2019.
25)
Contamination - Unexpected
If during development, contamination not previously identified is found to be present at the site, development work shall cease and not be recommenced until a report indicating the nature of the contamination and how it is to be dealt with has been submitted to, and approved in writing by, the local planning authority.ÿThe approved measures shall be implemented in full.
Reason - To ensure any risks from land contamination are minimised, and comply with the NPPF and development plan policies, in particular policy CE7 of the Local Plan 2019, and to accord withÿ CLR 11: Model Procedures for the Management of Land Contamination (Defra 2004) or the current UK requirements for sampling and testing).
26)
Roof structures and appliances
Except as shown on the approved drawings, no water tank, lift motor room, or other structure or appliance, shall be erected upon the roof.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, CL2 and CL6 of the Local Plan 2019.
27)
Code of Construction Practice
The development shall be carried out in accordance with the approved Code of Construction Checklist and Site Construction Management Plan (SCMP), approved under reference CON/21/00510, unless otherwise agreed in writing by the Local Planning Authority.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019.
28)
Accessible and Adaptable Dwellings
A minimum of 10% of all dwellings shall be built to requirement M4(3) wheelchair user dwellings contained within Part M volume 1 of the Building Regulations, as identified on the plans approved under condition 2 and thereafter maintained. All other dwellings shall be built to requirement M4(2) accessible and adaptable dwellings contained within Part M volume 1 of the Building Regulations and thereafter maintained.
Reason - To ensure satisfactory provision for people with disabilities and meet the changing needs of households in accordance with development plan policies in particular policy CH2 of the Local Plan 2019.
29)
Water consumption
Water efficient fixtures and fittings shall be provided in all residential units to achieve a water use target of no more than 105 litres per person per day.
Reason - To ensure efficient use of water and minimise waste, in accordance with Policy 5.15 of the London Plan (2016).
30)
Protection of trees during construction - Details required
The method(s) by which all existing trees on the site to be retained and those on adjacent land, are to be protected during site preparation, demolition, construction, landscaping, and other operations on the site including erection of hoardings, site cabins, or other temporary structures, shall be carried out in accordance with approval reference CON/21/00510, unless otherwise agreed in writing.
Reason - To ensure that the trees are adequately protected, to safeguard their contribution to the appearance and amenity of the area and accord with policies of the development plan, in particular policy CR6 of the Local Plan. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.
31)
Trees and landscaping - Details required
Prior to commencement on the relevant part of the development details of landscaping to include all existing trees and shrubs and proposed trees (including full details of all tree pits) and shrubs, hard and soft landscaping including pathways and their steps and slopes, lighting, and signage shall be submitted to and approved in writing by the local planning authority, and the development shall only be carried out and maintained in accordance with the details so approved.
Reason - To protect the appearance and amenity of the area and to accord with policies of the development plan, in particular policy CR6 of the Local Plan 2019
32)
Bird and Bat Boxes
The building shall not be occupied until details of a scheme of 'artificial nesting opportunities' have been submitted to and approved in writing by the Local Planning Authority. These details shall incorporate bird and bat boxes. The details to be submitted to the Local Planning Authority for approval shall include a timetable for provision and shall be implemented in accordance with the approved timetable and thereafter retained in accordance with the approved details.
Reason - To ensure that satisfactory provision is made for 'artificial nesting opportunities' within the development in accordance with Policy 7.19 of the London Plan (2011) and Policy CE4 of the Local Plan 2019.
33)
Generator Screening
Prior to commencement of the relevant part of the development details of the finishing and screening of the first floor generator shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details.
Reason - To preserve the character and appearance of the proposed building in accordance with policies CL1 and CL2 of the Local Plan 2019.
34)
Emergency Generator Testing
Any testing of the proposed emergency generators must take place between Monday and Friday after 09:00 and before 17:00 hour.
Reason - To preserve the living conditions of occupiers of neighbouring properties in accordance with policies CL5 and CE6 of the Local Plan 2019 and guidance contained in the Council's Noise Supplementary Planning Document.