1)
Time Limit
The development hereby permitted shall be begun before the expiration of three years from 26/01/2023, being the date of the original permission granted under ref. PP/22/06589.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.
2)
Compliance with approved drawings
The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.
3)
External materials
The development shall be carried out using external facing materials only as shown on the approved plans, and all new external brickwork shall match existing brickwork.
Reason - To ensure the completed development preserves the character and appearance of the Conservation Area.
4)
Code of Construction Practice
The development shall be carried out in accordance with the approved Appendix A Checklist and SCMP.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.
5)
Construction Traffic Management Plan (CTMP)
The development shall be carried out in accordance with the approved (application ref. CON/23/01221) Construction Traffic Management Plan. A one page summary of the requirements of the approved CTMP shall be affixed to the frontage of the site for the duration of the works at a location where it can be read by members of the public.
Reason - To minimise the impact of construction works upon highway safety and nearby residents' enjoyment of their properties in accordance with the Basements SPD and policies CL7, CT1 and CL5 of the Local Plan 2019.ÿ It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
6)
Professional management of engineering works
No development shall commence until
(A) a Chartered Civil Engineer (MICE) or Chartered Structural Engineer (MI Struct.E)ÿhas been appointed for the duration of building works and their appointment confirmed in writing to the Local Planning Authority, and
(B) the name, and contact details of the person supervising engineering and construction on site for the duration of building works have been confirmed in writing to the Local Planning Authority.ÿ
In the event that either the Appointed Engineer or Appointed Supervisor cease to perform that role for whatever reason before the construction works are completed, those works shall cease until a replacement chartered engineer of the afore-described qualification or replacement supervisor has been appointed to supervise their completion and their appointment confirmed in writing to the Local Planning Authority. At no time shall any construction work take place unless an engineer and supervisor are at that time currently appointed and their appointment has been notified to this Authority in accordance with this condition.
Reason - The details are considered to be material to the acceptability of the proposal, and for safeguarding the amenity of neighbouring residential properties and to comply with the Basements SPD and policy CL7 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan
7)
Considerate Constructors Scheme (CCS)
No development shall commence until such time as the lead contractor, or the site, is signed to the Considerate Constructors Scheme (CCS) and its published Code of Considerate Practice, and the details of (i) the membership, (ii) contact details, (iii) working hours as stipulated under the Control of Pollution Act 1974, and (iv) Certificate of Compliance, are clearly displayed on the site so that they can be easily read by passing members of the public, and shall thereafter be maintained on display throughout the duration of the works forming the subject of this permission.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements SPD and policy CL5 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
8)
Small-scale ground gas and vapour condition
A. No development shall commence (other than demolition above ground level) until an appropriate ground gas investigation is undertaken and a GVI report [where necessary incorporating a Remediation Strategy (RS)], is submitted to, and approved in writing by, the local planning authority.
B. No occupation or use of the development shall commence until the approved RS is implemented and a Verification Report (VR) is submitted to, and approved in writing by, the local planning authority.
Where physical remedial measures are implemented to protect end-users of the development they shall be maintained. The GVI, GVI Report, RS, VR and any unexpected contamination identified during the GVI and development shall be addressed in line with the Council's contaminated land guidance for small-scale ground gas and vapour protection.
Reason - To ensure any risks from ground gas and vapours and other contamination are minimised, to comply with the NPPF and development plan policies and in particular policy CE7 of the Local Plan 2019.
9)
Trees - lopping and topping
For the duration of works the tree(s) existing on the site at the date of this permission shall be protected so as to prevent damage above and below ground, and no tree shall be lopped, topped, or felled, or root pruned, without the prior written approval of the local planning authority.
Reason - To ensure that the trees are adequately protected, to safeguard their contribution to theÿappearance and amenity of the area and accord with policies of the development plan, in particular policy CR6 of the Local Plan 2019.
10)
Suitable Pump Device
The development hereby permitted shall not be occupied until a suitable pump device is installed.
Reason - To prevent sewer flooding, reduce flood risk and to contribute to sustainability in accordance with policy CL7 of the Local Plan 2019.