1)
Time Limit
The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.
2)
Compliance with approved drawings
The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.
3)
Submission of details (Full PP)
No development shall commence until full particulars of the following have been submitted to and approved in writing by the local planning authority and the development shall not be completed otherwise than in accordance with the details so approved:
(a) Detailed elevations and details of the doors, including elevations, head and jamb details of door and glazing and frames at a scale of 1:10
(b) Detailed elevations and details of the boundary wall with London Stock Brickat a scale of 1:10
Reason - To accord with the development plan by ensuring that the character and appearance of the area are preserved and living conditions of those living near the development suitably protected. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
4)
Sash windows in painted timber
The window/windows hereby permitted shall be timber framed, white painted, double hung, sliding sashes, and so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, CL2 and CL3 of the Local Plan 2019.
5)
Materials - To match existing
All work and work of making good shall be finished to match the existing exterior of the building(s) in respect of materials, colour, texture, profile and, in the case of brickwork, facebond and pointing, and shall be so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area in accordance with policies of the development plan in particular policies CL1, CL2, CL3 and CL6 of the Local Plan 2019.
6)
Sample panels required - Brickwork Courtyard Wall
Prior to the construction of the 'Brickwork Courtyard Wall', as shown on drawing number 4280 CDC XX XX DR A (GA) 408, a sample panel of the facing brickwork showing the proposed colour, texture, facebond and pointing shall be provided on site, and approved in writing by the local planning authority. The development shall be carried out in accordance with the details approved and the sample panel should be retained on site until the work is completed.
Reason - In order to preserve the character and appearance of the building and the wider conservation area, in accordance with policies CL2, CL3 and CL6 of the Local Plan 2019.
7)
Code of Construction Practice
No development shall commence until:
An Appendix A Checklist and Site Construction Management Plan (SCMP) for the development have both been submitted to, and approved in writing, by the Council's Construction Management Team, and then
B) Copies of the approved Checklist and Plan, and their written approval, have been submitted to the local planning authority to be placed on the property record.
The development shall be carried out in accordance with the Appendix A Checklist and SCMP so approved, or in accordance with a subsequent Checklist or SCMP as may be approved under this condition.
Note - The Council's Construction Management Team work independently of the planning department. For further information regarding the Code and how the required details should be submitted to them, the Council's Construction Management Team can be contactedÿon email at:ÿ[email protected]
or tel: 020 7361 3002
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.
8)
Travel Plan - Details reserved
The development hereby approved shall not be occupied until a travel plan has been submitted to, and approved in writing by, the local planning authority. The travel plan shall be monitored and reviewed in accordance with any targets within the plan, and such record made available upon request by the local planning authority.
Reason - To ensure the safe and sustainable movement of traffic on neighbouring highways, in accordance with policies of the development plan in particular policy CT1 of the Local Plan 2019.
9)
External Amenity Area and Crossover
No part of the external amenity area hereby approved shall be brought into use until the existing crossover to Princedale Road has been rebuilt to align with the gate hereby approved ÿand the footway in front of the siteÿhas been reinstated.
Reason - To maintain the quality of the footway, to protect the Borough's streetscape in accordance with CT1 (g) & CR4 (a)(g).
10)
Noise from building services plant and vents
Noise emitted by the air source heat pumps and air conditioning units, hereby permitted, when operating together or independently, shall not increase the existing lowest LA90 (15min) background noise level at any time when the plants are operating. The noise emitted shall be measured or predicted at 1.0m from the facade of the nearest residential premises or at 1.2m above any adjacent residential garden, terrace, balcony or patio. The plant shall be serviced regularly in accordance with manufacturer's instructions and as necessary to ensure that the requirements of the condition are maintained. If at any time the plant is unable to comply with this condition, it shall be switched off and not used again until it is able to comply.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Local Plan 2019.
11)
Anti-vibration mounts for air-conditioning/ extraction equipment
All air conditioning plant and equipment shall be supported on adequate prorietary anti-vibration mounts, as necessary, to prevent the structural transmission of vibration and regenerated noise within adjacent or adjoining premises, and these shall be so maintained thereafter. If at any time the plant is unable to comply with this Condition, it shall be switched off and not used again until it is able to comply.
Reason - To prevent any significant disturbance to residents of nearby properties and comply with development plan policies, in particular policy CL5 of the Local Plan 2019.
12)
Sustainable Urban Drainage System (SuDS) (for major and minor applications - implementation)
The development hereby permitted by this planning permission shall be carried out in accordance with the approved Flood Risk Assessment (dated May 2023), prepared by MHA Structural Design.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.
13)
Porous surfaces
All external hard surfacing in the development shall be constructed using porous materials and so maintained thereafter. If any permeable surfaces are removed, they must be replaced only with permeable surfaces.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.
14)
Contamination - Unexpected
If during development, contamination not previously identified is found to be present at the site, development work shall cease and not be recommenced until a report indicating the nature of the contamination and how it is to be dealt with has been submitted to, and approved in writing by, the local planning authority.ÿThe approved measures shall be implemented in full.
Reason - To ensure any risks from land contamination are minimised, and comply with the NPPF and development plan policies, in particular policy CE7 of the Local Plan 2019, and to accord withÿ CLR 11: Model Procedures for the Management of Land Contamination (Defra 2004) or the current UK requirements for sampling and testing).
15)
Provide cycle storage prior to occupation
The development shall not be occupied until the cycle storage facilities indicated on the approved plans have been fully implemented and made available for immediate use. The cycle facilities shall thereafter be retained for use at all times.
Reason - To ensure the safe and sustainable movement of traffic on neighbouring highways, in accordance with policies of the development plan in particular policy CT1 of the Local Plan 2019.