Drawing 181007C; Drawing 181008A and FIS Construction Products document regarding building design with regard to gas protection, not signed or dated, are refused for the discharge of conditions 37 and 40 attached to PP/16/01986
2)
Ground Investigation and Risk Assessment (Report Number 14514220446.505/B.0) Fox School, Kensington Place, Kensington, London, W8 7PP by Golder Associates (UK) Ltd, dated June 2016 and Appendix 'Drawing 1 - Borehole Locations' and Appendices A-G is approved for the discharge of conditions 36 and 39 attached to PP/16/01986
3)
Due to inconsistencies within the report and the lack of detail, the information submitted for conditions 37 and 40 fails to ensure that any risks from land contamination at construction stage are minimised, and comply with the NPPF and development plan policies, Policy CE7 of the Core Strategy, and accord with CLR 11: Model Procedures for the Management of Land Contamination (Defra 2004) or the current UK requirements for sampling and testing.