1)
Time Limit
The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.
2)
Compliance with approved drawings
The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.
3)
Materials - To match existing
All work and work of making good shall be finished to match the existing exterior of the building(s) in respect of materials, colour, texture, profile and, in the case of brickwork, facebond and pointing, and shall be so maintained.
Reason - To preserve the appearance of the building and/or the character of the area in accordance with policies of the development plan in particular policies CL1, CL2, CL3 and CL6 of the Local Plan 2019.
4)
Code of Construction Practice
No development shall commence until:
An Appendix A Checklist and Site Construction Management Plan (SCMP) for the development have both been submitted to, and approved in writing, by the Council's Construction Management Team, and then
B) Copies of the approved Checklist and Plan, and their written approval, have been submitted to the local planning authority to be placed on the property record.
The development shall be carried out in accordance with the Appendix A Checklist and SCMP so approved, or in accordance with a subsequent Checklist or SCMP as may be approved under this condition.
Note - The Council's Construction Management Team work independently of the planning department. For further information regarding the Code and how the required details should be submitted to them, the Council's Construction Management Team can be contactedÿon email at:ÿ[email protected]
or tel: 020 7361 3002
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.
5)
Flood Risk Assessment/Sustainable Drainage Systems Strategy
No development shall commence until a Flood Risk Assessment and Sustainable Drainage Systems Strategy with the following information is submitted to and approved in writing by the Local Planning Authority:
Flood Risk Assessment (FRA)
A Flood Risk Assessment to analyse all potential flood risks to the site and ensure that the development is protected against flood risk and will not lead to off-site flooding. Any proposed protection, mitigation and resilience measures should be shown on submitted plans.
Sustainable Drainage Systems (SuDS)
A detailed analysis of surface water run-off and attenuation volume (to demonstrate how the proposed measures will aim to comply with Local Plan Policy CE2 (g), which is to achieve a reduction of 50% of existing rates including climate change in the calculations and factoring in all flows into the sewer system including groundwater or other flows).
Information about the proposed SuDS types, their location, attenuation capacity, specification, structural integrity, construction, operation, access, and maintenance. (More sustainable green SuDS should be favoured over attenuation tanks).
Section/profile drawings of the SuDS, if relevant (green roofs, blue roofs, sub-base attenuation, permeable paving, planters, species, etc.).
Drainage plans to show clearly how surface water run-off will be conveyed to the SuDS and any connections to the sewer system if necessary.
During construction of the development hereby permitted the approved Sustainable Drainage System (SuDS) and Flood Risk measures shall be fully implemented and maintained thereafter.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan.ÿ It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the po
6)
Contamination - Unexpected
If during development, contamination not previously identified is found to be present at the site, development work shall cease and not be recommenced until a report indicating the nature of the contamination and how it is to be dealt with has been submitted to, and approved in writing by, the local planning authority.ÿThe approved measures shall be implemented in full.
Reason - To ensure any risks from land contamination are minimised, and comply with the NPPF and development plan policies, in particular policy CE7 of the Local Plan 2019, and to accord withÿ CLR 11: Model Procedures for the Management of Land Contamination (Defra 2004) or the current UK requirements for sampling and testing).
7)
Use of roof as terrace precluded
Except the area of the newly formed outdoor amenity area at the roof of the existing masonry closet wing and the recessed rear balcony at raised ground floor level (shown on drawings ref. 742/13 rev. A and 742/14 rev. A), the remainder parts of the flat roof of the existing closet wing adjacent to No. 17 Princedale Road together with the roof of the recessed first floor level solid closet wing extension forming the subject of this planning permission, shall not be used at any time as roof terraces.