1)
Time Limit
The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.
2)
Compliance with approved drawings
The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.
3)
Construction Traffic Management Plan (CTMP)
No development shall commence until a Construction Traffic Management Plan has been submitted to and approved in writing by the local planning authority. The statement should include:
a) routeing of demolition, excavation and construction vehicles, including a response to existing or known projected major building works at other sites in the vicinity and local works in the highway;
b) access arrangements to the site;
c) the estimated number and type of vehicles per day/week;
d) details of any vehicle holding area;
e) details of the vehicle call up procedure;
f) estimates for the number and type of parking suspensions that will be
required;
g) details of any diversion or other disruption to the public highway during preparation, demolition, excavation and construction work associated with the development;
h) work programme and/or timescale for each phase of preparation, demolition, excavation and construction work associated with the
development;
i) details of measures to protect pedestrians and other highway users from construction activities on the highway; and
j) where works cannot be contained wholly within the site a plan should be submitted showing the site layout on the highway including extent of hoarding, position of nearby trees in the highway or adjacent gardens, pedestrian routes, parking bay suspensions and remaining road width for vehicle movements.
The development shall be carried out in accordance with the approved Construction Traffic Management Plan. A one page summary of the requirements of the approved CTMP shall be affixed to the frontage of the site for the duration of the works at a location where it can be read by members of the public.
Reason - To minimise the impact of construction works upon highway safety and nearby residents' enjoyment of their properties in accordance with the Basements SPD and policies CL7, CT1 and CL5 of the Local Plan.ÿ It is necessary for the condition to be on the basis
4)
Considerate Constructors Scheme (CCS)
No development shall commence until such time as the lead contractor, or the site, is signed to the Considerate Constructors Scheme (CCS) and its published Code of Considerate Practice, and the details of (i) the membership, (ii) contact details, (iii) working hours as stipulated under the Control of Pollution Act 1974, and (iv) Certificate of Compliance, are clearly displayed on the site so that they can be easily read by passing members of the public, and shall thereafter be maintained on display throughout the duration of the works forming the subject of this permission.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements SPD and policy CL5 of the Local Plan 2015. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
5)
Code of Construction Practice
No development shall commence until:
A Code of Construction Checklist and Site Construction Management Plan (SCMP) for the development have been approved, in writing, by the Council's Construction Management Team, and then
B) Copies of the approved Checklist and Plan, and their written approval, have been submitted to the local planning authority to be placed on the property record.
[The Council's Construction Management Team work independently of the planning department. For further information regarding the Code and how the required details should be submitted to them, the Council's Construction Management Team can be contactedÿon email at:ÿ[email protected]
or tel: 020 7361 3002]ÿ
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2015. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
6)
Professional management of engineering works
No development shall commence until
(A) a Chartered Civil Engineer (MICE) or Chartered Structural Engineer (MI Struct.E)ÿhas been appointed for the duration of building works and their appointment confirmed in writing to the Local Planning Authority, and
(B) the name, and contact details of the person supervising engineering and construction on site for the duration of building works have been confirmed in writing to the Local Planning Authority.ÿ
In the event that either the Appointed Engineer or Appointed Supervisor cease to perform that role for whatever reason before the construction works are completed, those works shall cease until a replacement chartered engineer of the afore-described qualification or replacement supervisor has been appointed to supervise their completion and their appointment confirmed in writing to the Local Planning Authority. At no time shall any construction work take place unless an engineer and supervisor are at that time currently appointed and their appointment has been notified to this Authority in accordance with this condition.
Reason - The details are considered to be material to the acceptability of the proposal, and for safeguarding the amenity of neighbouring residential properties and to comply with the Basements SPD and policy CL7 of the Local Plan 2015. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan
7)
Protection of trees during construction - Details required
No development shall commence until full particulars of the method(s) by which all existing trees on the site and adjacent land (including the Magnolia tree at number 8) are to be protected during site preparation, demolition, construction, landscaping, and other operations on the site including erection of hoardings, site cabins, or other temporary structures, shall be submitted to and approved in writing by the local planning authority and the development shall be carried out only in accordance with the details so approved.
Reason - To ensure that the trees are adequately protected, to safeguard their contribution to theÿappearance and amenity of the area and accord with policies of the development plan, in particular policy CR6 of the Local Plan. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
8)
Planting and replanting
All tree and shrub planting forming part of the plans and details approved through this planning permission shall be carried out in the first planting and seeding season following the first occupation of the development or the completion of the development whichever is the sooner. Any trees or shrubs which, within a period of five years from the first planting and seeding season referred to above, die, are removed, or become seriously damaged or diseased, shall be replaced in the next planting season with others of similar size and species.
Reason - To protect the appearance and amenity of the area and to accord with policies of the development plan, in particular policy CR6 of the Local Plan.
9)
Submission of details (Full PP)
No development shall commence until full particulars of the following have been submitted to and approved in writing by the local planning authority and the development shall not be completed otherwise than in accordance with the details so approved:
(a) Detailed plan, section and elevations of proposed front entrance steps, including materials and external finishes
Reason - To accord with the development plan by ensuring that the character and appearance of the area are preserved and living conditions of those living near the development suitably protected. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
10)
Small-scale ground gas and vapour condition
A. No development shall commence (other than demolition above ground level) until an appropriate ground gas and vapour investigation (GVI) [incorporating the results of environmental and historical searches] is undertaken and a ground gas and vapour assessment report (GVAR) [where necessary incorporating a Remediation Strategy (RS)], is submitted to, and approved in writing by, the local planning authority.
B. No occupation or use of the development shall commence until the approved RS is implemented and a Verification Report (VR) is submitted to, and approved in writing by, the local planning authority.
C. Any unexpected contamination shall be addressed in line with the Council's CLC3 guidance. Where physical remedial measures are implemented to protect end-users of the development they shall be maintained. The GVI, GVAR, RS and VR shall be addressed in line with the Council's contaminated land guidance for small-scale ground gas and vapour protection.
Reason - To ensure any risks from ground gas and vapours and other contamination are minimised, to comply with the NPPF and development plan policies and in particular contaminated land policies of the Local Plan.
11)
Analysis of soils and fills condition
No occupation or use of the development shall take place until a description and the results of chemical analysis for soils and/or fills used at the development site, demonstrating their suitableness for use, is submitted to, and approved in writing by, the local planning authority. Work shall be undertaken in line with the 'Soil contamination testing for imported or reused soils and fills' guidance.