Case reference: PP/23/07749
Address: 17 and 18 Ovington Mews, LONDON, SW3 1LT
Ward: Brompton and Hans Town
Polling district: 02
Listed Building Grade:
Conservation area: Thurloe and Smith's Charity

Applicant details

Applicant's name: Darwish
Applicant company name: HOY Studio
Contact address: 50 Great Portland Street London W1W 7ND

Proposal details

Application type: PP (Planning permission)
Proposed development Amalgamation of numbers 17 and 18 Ovington Mews; excavation of single level of basement across the amalgamated properties; rearrangement of external windows to align with character of street; and relocation of roof lights
Date received: 23 Nov 2023
Registration date:
(Statutory start date)
02 Jan 2024
Public consultation ends: 02 Feb 2024
Application status: Decided
Target date for decision: 27 Feb 2024

Decision details

This case has not yet been decided.

Decision: Grant Planning Permission/Consent
Decision date: 30 Apr 2024
Conditions and reasons:

1)

Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.

2)

Compliance with approved drawings The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.

3)

Construction Traffic Management Plan (CTMP) No development shall commence until a Construction Traffic Management Plan has been submitted to and approved in writing by the local planning authority. The statement should include: a) routeing of demolition, excavation and construction vehicles, including a response to existing or known projected major building works at other sites in the vicinity and local works in the highway; b) access arrangements to the site; c) the estimated number and type of vehicles per day/week; d) details of any vehicle holding area; e) details of the vehicle call up procedure; f) estimates for the number and type of parking suspensions that will be required; g) details of any diversion or other disruption to the public highway during preparation, demolition, excavation and construction work associated with the development; h) work programme and/or timescale for each phase of preparation, demolition, excavation and construction work associated with the development; i) details of measures to protect pedestrians and other highway users from construction activities on the highway; and j) where works cannot be contained wholly within the site a plan should be submitted showing the site layout on the highway including extent of hoarding, position of nearby trees in the highway or adjacent gardens, pedestrian routes, parking bay suspensions and remaining road width for vehicle movements. The development shall be carried out in accordance with the approved Construction Traffic Management Plan. A one page summary of the requirements of the approved CTMP shall be affixed to the frontage of the site for the duration of the works at a location where it can be read by members of the public.
Reason - To minimise the impact of construction works upon highway safety and nearby residents' enjoyment of their properties in accordance with the Basements SPD and policies CL7, CT1 and CL5 of the Local Plan 2019.ÿ It is necessary for the condition to be on the

4)

Professional management of engineering works No development shall commence until (A) a Chartered Civil Engineer (MICE) or Chartered Structural Engineer (MI Struct.E)ÿhas been appointed for the duration of building works and their appointment confirmed in writing to the Local Planning Authority, and (B) the name, and contact details of the person supervising engineering and construction on site for the duration of building works have been confirmed in writing to the Local Planning Authority.ÿ In the event that either the Appointed Engineer or Appointed Supervisor cease to perform that role for whatever reason before the construction works are completed, those works shall cease until a replacement chartered engineer of the afore-described qualification or replacement supervisor has been appointed to supervise their completion and their appointment confirmed in writing to the Local Planning Authority. At no time shall any construction work take place unless an engineer and supervisor are at that time currently appointed and their appointment has been notified to this Authority in accordance with this condition.
Reason - The details are considered to be material to the acceptability of the proposal, and for safeguarding the amenity of neighbouring residential properties and to comply with the Basements SPD and policy CL7 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan

5)

Considerate Constructors Scheme (CCS) No development shall commence until such time as the lead contractor, or the site, is signed to the Considerate Constructors Scheme (CCS) and its published Code of Considerate Practice, and the details of (i) the membership, (ii) contact details, (iii) working hours as stipulated under the Control of Pollution Act 1974, and (iv) Certificate of Compliance, are clearly displayed on the site so that they can be easily read by passing members of the public, and shall thereafter be maintained on display throughout the duration of the works forming the subject of this permission.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements SPD and policy CL5 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.

6)

Code of Construction Practice No development shall commence until: A Code of Construction Checklist and Site Construction Management Plan (SCMP) for the development have been approved, in writing, by the Council's Construction Management Team, and then B) Copies of the approved Checklist and Plan, and their written approval, have been submitted to the local planning authority to be placed on the property record. [The Council's Construction Management Team work independently of the planning department. For further information regarding the Code and how the required details should be submitted to them, the Council's Construction Management Team can be contactedÿon email at:ÿ[email protected] or tel: 020 7361 3002]ÿ
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.

7)

Sash windows and doors in painted timber External windows and doors to the front elevation hereby permitted shall be timber framed and painted, with the windows being double hung, white painted, sliding sashes, and so maintained.
Reason - To preserve the appearance of the building and the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL2 of the Local Plan 2019.

8)

Conservation rooflights The rooflight(s) shall be of a traditional conservation type, flush with the roof and slim framed, and so maintained.
Reason - To preserve the appearance of the building and the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL2 of the Local Plan 2019.

9)

Positive pumped device The basement shall not be occupied until a suitable pumped device to protect the basement from sewer flooding has been installed and made available for use and shall be maintained as approved thereafter.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.

10)

Contamination - Site investigation and quantitative risk assessment No development shall commence (except for demolition above ground level) until the approved Proposed Intrusive Site Investigation Design (PSID) has been fully implemented and a report including full details of the intrusive site investigation, Risk Assessment (RA), an Options Appraisal (OA) and a Remediation Strategy (RS) has been submitted to, and approved in writing by, the local planning authority [The intrusive site investigation, RA, OA, RS and any associated reporting shall be undertaken in line with the Environment Agency's current Land Contamination Risk Management Guidance and the Council's guidance or any subsequent updates].
Reason - To ensure any risks from land contamination are both minimised and managed and to comply with the NPPF and development plan policies and in particular contaminated land policies of the Local Plan. It is necessary for the condition to be on the basis that 'No development shall commence (except for demolition above ground level) until' as ground works and building design need to be considered within the Options Appraisal and Remediation Strategy to ensure safe development, appropriate building design and in order to ensure an appropriate level of verification information is collected during the course of the development.

11)

Contamination - Verification report No occupation or use of the development shall occur until the approved Remediation Strategies are implemented and a Verification Report (VR) has been submitted to, and approved in writing by, the local planning authority [The VR shall include full details of requirements for ongoing monitoring and maintenance and be prepared in line with the Environment Agency's current Land Contamination Risk Management Guidance and the Council's guidance or any subsequent updates. Ongoing monitoring and maintenance shall be implemented in line with the approved Verification Report].
Reason - To ensure any risks from land contamination are both minimised and managed and to comply with the NPPF and development plan policies and in particular contaminated land policies of the Local Plan.

Informatives:

1)

Enforcement of Conditions (PP)
Your attention is drawn to the Conditions of this Permission and to the Council's powers of enforcement, including the power to serve a Breach of Condition Notice under the Town and Country Planning Act 1990, as amended. All Conditions must be complied with. If you wish to seek to amend a Condition you should apply to do so under s.73 of the Act, explaining why you consider it is no longer necessary, or possible, to comply with a particular condition.

2)

Variations to Approved Drawings
Planning permission is hereby granted for the development as shown on the approved drawings. Any variation to the approved scheme may require further permission, and unauthorised variations may lay you open to planning enforcement action. You are advised to seek advice from the Directorate of Planning and Place, before work commences, if you are thinking of introducing any variations to the approved development. Advice should urgently be sought if a problem occurs during approved works, but it is clearly preferable to seek advice at as early a stage as possible. Use the following link to see how advice can be obtained: Planning Advice Service

3)

Care in the Conservation Area
This property is within a Conservation Area. All building works should, therefore, be completed with great care. External facing work and detailed treatment should be finished in a manner sympathetic to the existing building. If there is any doubt about the way in which work should be carried out, you should seek the advice of the Directorate of Planning and Place.

4)

Unique text
Radon monitoring The UK Health Security Agency and HSE policy and guidance recommends and, in some cases, requires, that the owner and/or occupier of buildings undertake radon monitoring in all occupied and used basement areas. Radon monitoring should therefore be undertaken in line with these requirements. If monitoring identifies radon levels above the target level of 100Bq/m3 within a dwelling or above the relevant action level for occupational exposure, actions are recommended and for workplaces, may be required by the HSE. If radon is identified above 100Bq/m3 during future monitoring, please inform the Council at [email protected].

5)

Party Wall Act 1996
You are reminded of your duties under the Party Wall Act 1996. This requires a building owner to notify and obtain formal agreement from adjoining property freeholders and leaseholders and anyone who has had an interest of 12 months or greater, where the building owner intends to carry out work which involves: Work involving an existing shared wall with another property; Building on the boundary with another property; Excavating near a neighbouring building, and that work falls within the scope of the Act Notice should be served on neighbours at least one month before commencement of building works. Section 12(1) of the Act provides for the developer to provide security for neighbours through insurance or a security bond. Procedures under this Act are separate from the need for planning permission and for building regulations approval. Further guidance is available at: Party Wall Act 1996

6)

GTD/No pre-app/Est.Guid/No amend reqd
To assist applicants in finding solutions to problems arising in relation to their development proposals the Local Planning Authority has produced planning policies, and provided written guidance, all of which are available on the Council's website, and which has been followed in this instance.

7)

Unique text
The applicant is advised that the final CTMP required by condition 3, should address the following: a detailed site plan (scale of 1:200) must be submitted showing the proposed storage areas, loading and unloading areas, hoarding, spoil conveyor belt and the location of the concrete mixer. This plan must show the largest vehicle parked outside the site, with at least a 3m carriageway clearance. This is essential to ensure the success of the scheme; Q7 - all residents on Ovington Gardens and Ovington Square must be consulted on the CTMP, as well as all the residents of Ovington Mews and the Knightsbridge Residents' Association; Q8 - the Full CTMP must confirm that all vehicles will follow the statedconstruction route, not just 'where relevant'; Q10 - the Full CTMP must confirm whether there will be any deliveries outside of the stated hours (9.30am - 4.30pm); Q12 - Appendix C does not show emergency vehicle access. This must therefore be provided; Q18 - the size of the small tipper must be corrected to ensure the document is accurate; Q18 - it is stated that 'timings will be agreed in advance with surrounding neighbours, scheduled to fit around the neighbour's programme, to ensure they have access to their properties.' It is noted that in answer to Q11, it is stated that 'access will be maintained for all neighbouring properties.' It must be ensured that the construction work does not inhibit the neighbours movements and Q18 must be updated accordingly; Q20 - a plan showing how pedestrians will be protected must be submitted; Q22, Q23, Q25 and Q28 use indeterminate language and must be updated with clear commitments; and, Q25 - The 'Summary of CTMP Requirements' states that there will be a need to suspend the single yellow line to the front of the site however, this is not relevant to Q25 which relates to road closures. This information must be moved to Q28.

8)

Highways Technical Approval-Sep Approval
You are advised that Technical Approval in accordance with the Design Manual for Roads and Bridges BD2/12 will be required for any structural works/alterations/repairs to structures over, under or adjacent to the public highway.ÿThe procedures only grant approval under the Highways Act. The granting of planning permission and building consent does not imply that such approval is given. Please contact the Directorate of Transportation and Highways for advice on 020 7341 5220 or email [email protected].

Committee details

Decision by: This case is currently due to be decided under delegated powers.

Appeal details

This case has not been appealed.

Planning Inspectorate reference number:
Appeal received:
Appeal type:
Appeal procedure:
Appeal start date:
Deadline for comments to be received by the Planning Inspectorate:
Appeal decision:
Appeal decision date:

Contact details

Planning case officer: Julia Drzewicka
Planning team: South
Email: [email protected]
Telephone: 020 7361 3012