1)
Time Limit
The development hereby permitted shall be begun before the expiration of three years from 08/03/2022 being the date of the original permission granted under ref. PP/22/00074.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.
2)
Compliance with approved drawings
The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.
3)
Accord with approved CTMP
The development shall not be carried out except in accordance with the approved Construction Traffic Management Plan approved under CON/22/01792 .
Reason - To minimise the impact of construction works upon highway safety and nearby residents' enjoyment of their properties, in accordance with the Basements SPD and policies CT1, CL5 and CL7 of the Local Plan 2019.
4)
Professional management of engineering works
Development shall be carried out under the supervision of Trevor Vincent Bsc C.Eng M.I.Struct.E. as confirmed in writing by the applicant.
In the event that either the Appointed Engineer or Appointed Supervisor cease to perform that role for whatever reason before the construction works are completed, those works shall cease until a replacement chartered engineer of the afore-described qualification or replacement supervisor has been appointed to supervise their completion and their appointment confirmed in writing to the Local Planning Authority. At no time shall any construction work take place unless an engineer and supervisor are at that time currently appointed and their appointment has been notified to this Authority in accordance with this condition.
Reason - The details are considered to be material to the acceptability of the proposal, and for safeguarding the amenity of neighbouring residential properties and to comply with the Basements SPD and policy CL7 of the Local Plan 2019. It is necessary for the condition to be on the basis that 'No development shall commence until' as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan
5)
Considerate Constructors Scheme (CCS)
No development shall commence until such time as the lead contractor, or the site, is signed to the Considerate Constructors Scheme (CCS) and its published Code of Considerate Practice, and the details of (i) the membership, (ii) contact details, (iii) working hours as stipulated under the Control of Pollution Act 1974, and (iv) Certificate of Compliance, are clearly displayed on the site so that they can be easily read by passing members of the public, and shall thereafter be maintained on display throughout the duration of the works forming the subject of this permission.
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements SPD and policy CL5 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Development Plan.
6)
Code of Construction Practice
No development shall commence until:
An Appendix A Checklist and Site Construction Management Plan (SCMP) for the development have both been submitted to, and approved in writing, by the Council's Construction Management Team, and then
B) Copies of the approved Checklist and Plan, and their written approval, have been submitted to the local planning authority to be placed on the property record.
The development shall be carried out in accordance with the Appendix A Checklist and SCMP so approved, or in accordance with a subsequent Checklist or SCMP as may be approved under this condition.
Note - The Council's Construction Management Team work independently of the planning department. For further information regarding the Code and how the required details should be submitted to them, the Council's Construction Management Team can be contactedÿon email at:ÿ[email protected]
or tel: 020 7361 3002
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.
7)
Small-scale ground gas and vapour condition
A. Development shall be done in compliance with the small scale ground gas and vapour report approved under CON/22/03157.
B. No occupation or use of the development shall commence until the approved RS is implemented and a Verification Report (VR) is submitted to, and approved in writing by, the local planning authority.
Where physical remedial measures are implemented to protect end-users of the development they shall be maintained. The GVI, GVI Report, RS, VR and any unexpected contamination identified during the GVI and development shall be addressed in line with the Council's contaminated land guidance for small-scale ground gas and vapour protection.
Reason - To ensure any risks from ground gas and vapours and other contamination are minimised, to comply with the NPPF and development plan policies and in particular policy CE7 of the Local Plan 2019
8)
Pumped device
Prior to occupation of any part of the basement, a suitable pumped device shall be provided within the basement and be so maintained thereafter.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.
9)
Sustainable Urban Drainage Systems
The development hereby approved shall be carried out in accordance with the Sustainable Drainage Systems (SuDS) Report for Planning, by Ferguson Brown, reference 2021-12-23, unless agreed otherwise in writing by the Local Planning Authority.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.
10)
Materials - To match existing
All work and work of making good shall be finished to match the existing exterior of the building(s) in respect of materials, colour, texture, profile and, in the case of brickwork, facebond and pointing, and shall be so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area in accordance with policies of the development plan in particular policies CL1, CL2, CL3 and CL6 of the Local Plan 2019.
11)
Black painted railings
The railings hereby approved shall be painted black, and so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL6 of the of the Local Plan 2019.
12)
Sash windows in painted timber
The window/windows hereby permitted, expect those on the lower ground and ground floor rear extension, shall be timber framed, white painted, double hung, sliding sashes, and so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, CL2 and CL3 of the Local Plan 2019.
13)
Submission of details (Full PP)
Detailed drawings or samples of materials as appropriate, in respect of the following, shall be submitted to and approved in writing by the local planning authority before the relevant part of the work is begun, and the works shall not be carried out other than in accordance with the details so approved and shall thereafter be so maintained:
(a) Elevation (1:10) and section (1:5) drawings of new windows and French doors with details of mouldings in section (1:1) and a plan showing locations of retained / historic doors and new doors. New windows and doors shall be made of solid timber and hand painted;
(b) A sample panel of the bricks to be used in the reconstruction of the rear facade, showing the colour, size, texture and bond of brick and colour and profile of pointing. The sample panel shall be constructed and retained on site throughout the construction phase and all replacement brick work built in accordance with the panel and maintained as such.
Reason - To accord with the development plan by ensuring that the character and appearance of the area are preserved and living conditions of those living near the development suitably protected.