Case reference: PP/24/01147
Address: The Estates Office, Cheyne Court, LONDON, SW3 5TP
Ward: Royal Hospital
Polling district: 16
Listed Building Grade: N/A
Conservation area: N/A

Applicant details

Applicant's name: Enteraden Ltd
Applicant company name: Urban Hang Suite
Contact address: Wandsworth Bridge Road LONDON SW6 2TF

Proposal details

Application type: PP (Planning permission)
Proposed development Alterations and side extension to the estate office with rooflight and alterations to a refuse store.
Date received: 19 Feb 2024
Registration date:
(Statutory start date)
19 Feb 2024
Public consultation ends: 15 Mar 2024
Application status: Decided
Target date for decision: 15 Apr 2024

Decision details

This case has not yet been decided.

Decision: Grant Planning Permission/Consent
Decision date: 15 Apr 2024
Conditions and reasons:

1)

Time Limit The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason - As required by Section 91 of the Town and Country Planning Act 1990, to avoid the accumulation of unexercised Planning Permissions.

2)

Compliance with approved drawings The development shall not be carried out except in complete accordance with the details shown on submitted plans
Reason - The details are material to the acceptability of the proposals, and to ensure accordance with the development plan.

3)

Code of Construction Practice No development shall commence until: An Appendix A Checklist and Site Construction Management Plan (SCMP) for the development have both been submitted to, and approved in writing, by the Council's Construction Management Team, and then B) Copies of the approved Checklist and Plan, and their written approval, have been submitted to the local planning authority to be placed on the property record. The development shall be carried out in accordance with the Appendix A Checklist and SCMP so approved, or in accordance with a subsequent Checklist or SCMP as may be approved under this condition. Note - The Council's Construction Management Team work independently of the planning department. For further information regarding the Code and how the required details should be submitted to them, the Council's Construction Management Team can be contactedÿon email at:ÿ[email protected] or tel: 020 7361 3002
Reason - To mitigate the impact of construction work upon the levels of amenity that neighbouring occupiers should reasonably expect to enjoy, and to comply with the Basements and Transport and Streets SPDs and policies CL5, CT1, CE5 and CE6 of the Local Plan 2019. It is necessary for the condition to be on the basis that "No development shall commence until" as compliance with the requirements of the condition at a later time would result in unacceptable harm contrary to the policies of the Local Plan 2019.

3)

Sash windows and doors in painted timber External windows and doors hereby permitted shall be timber framed and painted, with the windows being double hung, white painted, sliding sashes, and so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL2 of the Local Plan 2019.

5)

Conservation rooflights The rooflight(s) shall be of a traditional conservation type, flush with the roof and slim framed, and so maintained.
Reason - To preserve or enhance the appearance of the building and/or the character of the area, in accordance with policies of the development plan in particular policies CL1, and CL2 of the Local Plan 2019.

6)

Privacy (Obscured glazing) The window(s) hereby permitted shall be obscurely glazed, and shall be so maintained.
Reason - To safeguard the privacy of neighbouring property, and so accord with policy CL5 of the Local Plan 2019.

7)

Green Roof - Implementation During construction of the development hereby permitted the green roof as shown in the approved drawings shall be fully implemented and maintained thereafter.
Reason - To reduce flood risk and to contribute to sustainability in accordance with policy CE2 of the Local Plan 2019.

Informatives:

1)

GTD/No pre-app/Amendmts to comply Est. G
To assist applicants in finding solutions to problems arising in relation to their development proposals the Local Planning Authority has produced planning policies, and provided written guidance, all of which are available on the Council's website. A pre-application advice service is also offered, although not used in this instance. On first submission the proposals did not comply with guidance, but improvements suggested by the planning authority were adopted by the applicant.

2)

Enforcement of Conditions (PP)
Your attention is drawn to the Conditions of this Permission and to the Council's powers of enforcement, including the power to serve a Breach of Condition Notice under the Town and Country Planning Act 1990, as amended. All Conditions must be complied with. If you wish to seek to amend a Condition you should apply to do so under s.73 of the Act, explaining why you consider it is no longer necessary, or possible, to comply with a particular condition.

3)

Conditions - Precedent to Commencement
Conditions no 3 impose requirements which must be met prior to commencement of the development. Failure to observe these requirements could result in the Council taking enforcement action, or may invalidate the planning permission and render the whole of the development unlawful.

4)

Variations to Approved Drawings
Planning permission is hereby granted for the development as shown on the approved drawings. Any variation to the approved scheme may require further permission, and unauthorised variations may lay you open to planning enforcement action. You are advised to seek advice from the Directorate of Planning and Place, before work commences, if you are thinking of introducing any variations to the approved development. Advice should urgently be sought if a problem occurs during approved works, but it is clearly preferable to seek advice at as early a stage as possible. Use the following link to see how advice can be obtained: Planning Advice Service

5)

Building Regs - Separate Approval
Separate approval for the works hereby granted permission/consent may be required by the Building Act 1984 and the Building Regulations 2018 (as amended), and the grant of planning permission does not imply that such approval will be given. The District Surveyor, Town Hall, Hornton Street, W8 7NX should be consulted before works commence.

6)

Unique text
Due to the small-scale nature of the works, under best practice guidance MoL SPG 'The Control of Dust and Emissions from Construction & Demolition Sites' and the IAQM's 'Assessment of dust from demolition and construction' the site would be determined as 'Low Risk' with regards to dust impacts. Any Environmental Management Plans, Construction Management Plans or Construction Traffic Management Plans should reference these guidance documents and include a list of the appropriate mitigation measures to be utilised on site where necessary. The physical onsite inspection for the generation of dust and soiling effects will be sufficient in this case when utilised alongside other mitigation measures.

Committee details

Decision by: This case is currently due to be decided under delegated powers.

Appeal details

This case has not been appealed.

Planning Inspectorate reference number:
Appeal received:
Appeal type:
Appeal procedure:
Appeal start date:
Deadline for comments to be received by the Planning Inspectorate:
Appeal decision:
Appeal decision date:

Contact details

Planning case officer: Jonathan Kwok
Planning team: South
Email: [email protected]
Telephone: 020 7361 3012

Comment on this application

The consultation period for this application has ended.

Documents related to case PP/24/01147